Apartment residents are living wrapped in plastic

Scaffolding was put up and workmen started removing the cladding in April this year, but plastic sheeting still shrouds the 250m( 820 ft)-long building.

Avatar photo

Published

on
Flats covered in plastic. (Anita Maric via SWNS)

By Jack Evans via SWNS

Residents in an award-winning multi-million pound apartment complex are “living in permanent darkness” after the entire building was wrapped in PLASTIC.

Huge sheeting covers every inch of the six-story high Islington Gates tower while the dangerous cladding is replaced with a non-flammable material.

But due to delays in having the work done, residents in the 141 flats in the Jewellery Quarter of Birmingham, England have been unable to see out of their windows for six months.

Flats covered in plastic as cladding is removed at Islington Gates, Birmingham. (Anita Maric via SWNS)

“We used to have views across the city but now the plastic completely blocks the light. It’s pretty miserable," saidJennifer Reid, 40.

“It is dark and cold and compounded by the fact they’ve taken the bricks out and it’s starting to get darker now so you have to have your lights on all of the time.”

Leaseholders who paid between £160,000 and £200,000( $220,874- $276,093) for the apartments are also facing five-figure bills to put up the new cladding.

Many residents are first-time buyers who bought the properties with mortgages before a fire safety review outlawed certain cladding following the Grenfell fire tragedy. The review found Islington Gates' aluminium and cedarwood cladding were different to that at Grenfell, but were still too flammable and needed replacing.

Scaffolding was put up and workmen started removing the cladding in April this year, but plastic sheeting still shrouds the 250m( 820 ft)-long building.

Jennifer Reid who lives at Islington Gates, Birmingham.(Anita Maric via SWNS).

Jennifer bought her one-bedroom sixth-story flat in February 2019 and found out later that year there was a “significant fire safety issue."

“It’s been a really tricky, horrible two years having committed to buy the flat and then learning I was on the hook for a pretty huge bill," said the marketing manager.

“The government are now going to be funding a significant portion of the work, but my initial bill was £50,000, that’s on a £160,000 flat. Now it is about £30,000 that will be covered but I’m still on the hook for a serious amount of money.

"I'm already mortgaged up to my eyeballs. It could be over £10,000 and on top of that my service charge had doubled as well from £1,400 to £2,800-a-year.

"This all happened and then COVID happened so I’ve been working from home."

As well as being denied a view and living in permanent gloom, residents have also complained about leaking ceilings and mold.

“When there was heavy rain a few months ago water got into my flat through a hole in the concrete," saidlegal professional Danny Kelly, 30, who has been a leaseholder on the sixth floor since 2018 and lives with his 27-year-old fiancée Danielle Poole.

"It got into my light sockets and fused all my lights. Then around the windowsill the water gets in and I can’t even open them to get rid of the mold which will be an even bigger problem over winter.”

Danny Kelly (Anita Maric via SWNS)

Danny said leaseholders were told the building’s repair bill was £9million ( $12, 424,185) and his share ran to £75,000($103,534).The five-figure bill he faces has forced them to put their marriage plans on hold.

“We were told we didn’t have the same cladding as Grenfell, so we thought ‘great’ but government advice changed and it fell within the scope of what needed to be removed," he said.

“We had some timber and panel-style cladding which was too flammable. They also discovered fire safety defects like there being no fire breaks. They had been signed off as having been put in but they hadn’t. We had wooden balconies which needed to be removed."

The Government's Building Safety Fund, announced in the 2020 spring budget, reduced his bill but still left him out of pocket.

“It’s gone down to £10,000 or £11,000 but it’s still five figures," Danny said.

“The leaseholders are the only party not a fault at all. The developers, planners, builders, contractors, surveyors have all made mistakes.

Danny Kelly's flat covered in plastic. (Anita Maric via SWNS)

"Now the cladding’s off, it’s the disruption from the work and the wet and cold that are the issues.When the wind blows the scaffolding pipes it makes a drumming noise and that’s throughout the night.

“In the day the workmen are two meters from my desk – the drilling, knocking out the brick out is very loud. There’s no privacy because there are people walking past every day. I either let people see in or close my blinds all day.

“And I’ve lost my view because of the plastic. There’s no sunlight, I can’t tell what the weather is. My balcony used to overhang the canal, so it was a nice view. I was shielding last year so I couldn’t go outside and that was the only fresh air I had.

“We were told the work would be done by the end of October but we are there now and there is no sign of it.”

Shabana Mahmood, the Labour MP for Birmingham Ladywood, has been an advocate for leaseholders.

Balcony closed notice. (Anita Maric via SWNS)

"While it's welcome that the cladding works have finally started, there are already significant delays," she said.

“The damage to flats is completely unacceptable. These issues are driving many leaseholders to the brink of financial ruin and only compounding the significant toll on the mental health of my constituents."

The award-winning Islington Gates, comprising of apartments, offices and restaurants was built on the banks of the Birmingham and Fazeley Canal at a cost of £30million ( $41,413,950) and was completed in 2018.

Philip Davis, Chair of Islington Gates’ Leaseholder Management Board, said: “The Leaseholder Board is well aware of the unpleasant conditions imposed by the removal of the cladding.

Flats covered in plastic as cladding is removed at Islington Gates, Birmingham.(Anita Maric via SWNS)
« of 8 »

“Working with our Building Consultants and the works contractor Woodman Bros. Ltd., we are doing all we can to get the fire safety works finished.

"The Government grant paying for some of the fire safety costs makes no provision for funding alternative accommodation.

"Any such cost would fall on all leaseholders and is not sustainable given the already substantial costs we all face for the building industry’s negligence.

"Unfortunately the plastic sheeting covering the site and other impacts of the works are unavoidable as we push forward with the £8million plus fire safety works."

Stories and infographics by ‘Talker Research’ are available to download & ready to use. Stories and videos by ‘Talker News’ are managed by SWNS. To license content for editorial or commercial use and to see the full scope of SWNS content, please email [email protected] or submit an inquiry via our contact form.